Swift River Energy Limited (SREL) is the builder, owner and operator of the Bala Generating Station. Starting as early as September 18, 2019 and continuing for up to 3 weeks, Swift River will be carrying out controlled and incremental testing of the power plant and prepare the facility for operations. Testing will be carried out from 7am - 6pm for 7 days a week during this period.

Members of the public and stakeholders can be assured that the testing procedures have been prepared by experts. Plans have been carefully developed with the Ministry of Natural Resources and Forestry and Ontario Power Generation. During testing, SREL will be coordinating with them several times a day. Daily variations in water flows will cause some fluctuation of water levels. However, the test program has been prepared to maintain water levels within the Best Management Zone as outlined in the Muskoka River Water Management Plan for various reservoirs from Lake Muskoka to Go Home Lake. The MNRF will continue to operate the Bala North and South Dam during this time.

During testing, the public is advised to exercise caution. SREL will be monitoring the vicinity of the Bala Generating Station and dams but the public is requested to assist by remaining clear of the area immediately adjacent to the station during this period.

For any questions or concerns or updates, please call, send us an email, or follow us on Twitter. We will endeavor to respond within 24 hours. In the case of an emergency, please call 911.

Toll Free: 1-877-389-4099

Email: info@balafalls.ca

Twitter: @balafallshydro

Web: balafalls.ca

March 2019 Newsletter

Swift River Energy Limited is hiring a local operator for the hydro plant in Bala. More details are available in this month’s newsletter.

Newsletter - March 2019

Correction: Please note a previous version of the newsletter should read: "At the end of March, we will be conducting one final controlled blast at the tailrace, where water exits the power plant. The blast will require one road closure, lasting less than 15 minutes. Mail notifications have been sent to nearby land owners." A previous version of the newsletter indicated that this work would not impact street traffic.

 

June 2018 Newsletter

Hello summer, welcome back! A lot has changed in the last few months on the construction site for the North Bala Small Hydro Project.

Newsletter - June 2018

Correction: Please note a previous version of the newsletter should read: "After Bala's power plant is up and running, our company will operate these dams." instead of "After Bala's power plant is up and running, our company will own and operate these dams."

February 2018 Newsletter

Swift River Energy Limited continues construction in the North Bala Small Hydro Project.  The upstream coffer dam at Bala's North Dam was successfully removed at the end of February.  The operation was executed smoothly. As part of our ongoing engagement with the community, here's what you need to know about our activities.

Newsletter - Feb 2018

Construction newsletter

Swift River Energy Limited has been authorized to proceed with the North Bala Small Hydro Project by federal, provincial, municipal, and local regulators.  Construction began in August and is expected to take up to 2 years. As part of our ongoing engagement activities, this is the first of our newsletters to give you what you need to know about our construction activities.

Newsletter Oct 2017 

Portage Landing Park Plan - Open house

Swift River Energy Limited thanks everyone that came out to the open house last night. 

Approximately 60 members of the community came out to review the rehabilitation plans and meet with representative(s) of The Township of Muskoka Lakes, Steven Burgess Architects and Swift River Energy Limited. 

Comments, opinions, and suggestions were received and are appreciated. 

Park Plan - Open house, Bala ON

The public is invited to attend an informational open house at Bala Community Centre  at 1008 Maple Avenue, Bala on December 8, 2016 from 4:30 pm – 7:30 pm  to inspect the plans to restore Portage Landing in Bala. 

At the open house you will have an opportunity to speak with representatives of Swift River Energy Limited, Township of Muskoka Lakes, and Stevens Burgess Architects

New balafalls.ca

Welcome to Swift River Energy Limited’s new website for the North Bala Falls Small Hydro Project!  Here you will find news, drawings and next steps for the construction of the small power plant. 

SREL is currently working towards completing the power plant building drawings for the submission of a building permit and completing power plant plans and specifications for submission to the Province of Ontario.  Both submissions are several weeks away.  We have also been busy working with TML staff, Council and consultants on a plan to mitigate construction impacts to traffic and Margaret Burgess Park.  The plan includes leasing land from TML to avoid using the park for construction staging.  TML Council will be considering the lease option soon (possibly at the November 13th Council meeting) and, depending on which option they  choose, a new accessible water front park located on the Portage Landing Lands could be in Bala’s future. 

You can check out the proposed park Plans, which also include the power plant building's elevation drawings. 

Did you know that the design committee who developed the plans for the hydro dam were made up of individuals in the community worked closely with SREL’s architect on the development of the building design?